View Information about the Services Available from Lakehead Constructors, Inc. in Superior, Wisconsin and Aurora, Minnesota
 

Wastewater Treatment Improvement Project and new Water Treatment Plant

Project(s): Wastewater Treatment Improvement Project and new Water Treatment Plant

Owner: City of Two Harbors, MN

Value: $36 million 3-year schedule

Scope of Work: as GC built a new water treatment facility on the shores of Lake Superior. Also, a significant upgrade to their existing WWTF included – new raw water pumps, grit removal, separation equipment, new aeration basins, final clarifiers, and pumps, new biosolids treatment facility, chlorine feed rooms, new operations building with chemical feed, SCADA systems, locker room, lab, and breakroom.